EPT Heater Pad User’s Manual

February 29, 2012

I.  Introduction

The following flexitank blog post will explain how to properly use the EPT Heater Pad.

a.  Materials of Construction

The Heater Pad has a continuous one piece HDP/Valuflex hose for hot water or steam to flow through for heating product inside the flexitank.

b.  Use and Limitations

The Heater Pad uses low pressure steam or hot water.  Do not use high pressure steam as this could damage the flexitank.


II.  Installation

a.  Container Preparation

It is very important to prepare the container properly and thoroughly.  If the walls or floor of the container are in bad condition, do not use.

Step 1 

Open container and sweep out all dust and dirt.

Step 2

Inspect the container floor for nails, screws, or anything else that might puncture the flexitank.  Remove any sharp objects on the floor.  Use duct tape or corrugated cardboard to cover any rough spots on the floor of the container (NEVER PUT CARDBOARD ON TOP OF HEATER PAD).

b.  Heater Pad Preparation

Step 1

Pull the tape off of the heater pad roll.  DO NOT CUT OFF.

Step 2

Roll Heater PadPlace the heater pad on the floor of the container near the doors.  Make sure that the inlet and outlet hose are at the rear (door end) of the container.  Unroll the heater pad toward the front of the container (away from the doors).  The unit should be centered in the container and close enough to the doors to access the inlet and outlet hose.

Make sure that the hose lays flat on floor without running up the container wall.  Avoid KINKS in the hose.  Taping the ends of the hose down can help.

Heater Pad Rolled Out

Step 3

Line up the inlet/outlet hose to the back of the bulkhead panel.  Cut two holes 1” x 1” in the bottom of the bulkhead panel to pull the inlet and outlet hose through.

DO NOT STACK BULKHEAD PANEL ON HEATER HOSE OR HEATER PAD.

Inlet and Outlet Hose

The heater pad is now completely installed.


III. Product Discharging

The front of the container must be inclined to completely discharge the flexitank.

 a.  Heating Procedure

Step 1

Install the required fittings to the inlet and discharge hoses.  These are not provided with the heater pad.  It does not matter which side is used for inlet or outlet.

Step 2

Connect the heater pad inlet and outlet hoses to the hot water system being used at the discharge location.

Step 3

Circulate the hot water until the product temperature has been elevated as required for discharge.

This is the sixth in the series of Flexitank Training Posts.


IV. Related Links

For a pdf copy of this post including exact heater pad specifications, click the following link which will take you to the LinkedIn Profile of EPT Flexitank Sales Manager, Jennifer Phillips.  Scroll down to the bottom and click EPT Heater User’s Manual.  You may need to log into your existing LinkedIn account.

Click one of the following links to go to an earlier Flexitank Training post:

How To Select A Flexitank Container

How To Prepare A Flexitank Container

How To Load A Bottom Discharge Flexitank

How To Load A Top Discharge Flexitank

How to Discharge A Flexitank

Click the following link for more information on EPT Flexitank Training


EPT Expands Into Guatemala

February 22, 2012

Flexitank technology leader, Environmental Packaging Technologies Ltd (EPT), Houston, is proud to announce the continued expansion of its Central American network into Guatemala with its partner, Euromex Logistica Intl. & Top Traders. With the opening of this new depot, EPT’s Big RED Flexitank will now be available in Guatemala to service the palm oil and latex markets.

“This expansion is representative of both the success our products and of our strong partnership with Euromex” stated Roger Goose, Vice President of Sales for EPT. “Our combined commitment to quality and service has given us the opportunity to bring the Big Red difference to Guatemala.”

The addition of the Guatemalan depot further strengthens EPT’s position in Central America. Euromex’s depot network include Guadalajara, Toluca, Monterrey, Tampico, Mazatlán, Veracruz, Manzanillo and México City.

About Environmental Packaging Technologies

Environmental Packaging Technologies, Ltd. provides global bulk packaging solutions for the transportation and storage of non-hazardous, flowable products.

For more information about EPT and its expansion, call EPT global sales manager, Jennifer Phillips at 713-961-2795 or email jennifer@eptpac.com.


How To Discharge A Flexitank

February 15, 2012

The front of the container must be inclined to completely discharge the flexitank.

  1. Place the suction pump at a convenient spot between the container and the storage tank.
  2. Open the right hand door of the container only.  The left hand door must be closed at all times during the discharging process.
  3. Open the snout of the wear sleeve (do not cut) and remove the safety plug on the product valve.
  4. Connect the cam-lock coupling of the inlet hose of the pump to the product valve on the flexitank and connect the outlet hose to the storage tank, making sure that these two couplings are properly connected.  Depending on hose size, a reducer may be required as shown below:

    Coupling and Reducer

  5. Move the handle of the product valve to the open position and turn on the pump to start the discharging process.  Make sure that the product hose is properly supported to prevent pulling downward on the product valve.  One method is shown below:

    Support Product Hose

  6. When the product has been 75% to 80% discharged, reduce the pump rate.  When the liquid in the flexitank is lowered to approximately 4 inches (10 cm) from the floor level, 1 to 2 workers must go inside the container to lift up the sides of the flexitank to move the product into the center.  Leave the sides of the flexitank folded over.

    Fold Sides of Flexitank

  7. Lift the front end of the flexitank and roll slowly towards the door so that the liquid residue can flow easily towards the product valve.  Continue the process until the liquid inside the flexitank is totally pumped off.

    Roll Towards Door
    NOTE: For some products, the flexitank is easier to empty if a large, flat tool (i.e. squeegee or the back side of a push broom) is used on the outside of the flexitank to push product toward the product valve.

  8. Close the product valve and turn off the suction pump.  Remove the coupling from the product valve.  Replace the safety plug on the product valve.
  9. Open the left container door and dismantle the bulkhead.
  10. Roll up the flexitank and wear sleeve.  Place them with the bulkhead and support beams.
  11. Close the container doors.
  12. Remove Bulk Liquid Caution labels/decals from the container.

The discharging process is complete.

For a pdf copy of this post, click the following link which will take you to the LinkedIn Profile of EPT Flexitank Sales Manager, Jennifer Phillips. Scroll down to the bottom and click How To Discharge A Flexitank. You may need to log into your existing LinkedIn account.

This is the fifth in the series of Flexitank Training Posts.

Click one of the following links to go to an earlier Flexitank Training post:

How To Select A Flexitank Container

How To Prepare A Flexitank Container 

How To Load A Bottom Discharge Flexitank

How To Load A Top Discharge Flexitank 

Click the following link for more information on EPT Flexitank Training

 


How to Load A Top Discharge Flexitank

February 8, 2012
  1. Inspect the flexitank for proper installation. Be sure to check the following items:

    a.  Make sure that the flexitank has been properly unrolled completely against the walls of the container and into the corners. The flexitank should be secured to the container in all corners.

    b. Check that the flexitank valve is positioned correctly.

    c.  Verify the capacity of the flexitank to avoid under or over-filling. Flexitanks can be under or over loaded by up to 2% of the total capacity of the flexitank.

    NOTE: Under or over filling beyond above recommendations may void manufacturer’s warranty.

    d.  Effective temperature range is 167°F to -23°F or 75°C to -5°C.

  2. Remove the safety cap and locking pin. Pull the lever of the flexitank valve outward to ensure that the ball valve is fully opened.
  3. Fit the cam-lock coupling of the loading hose properly to the valve and lock into place. Make sure that the loading hose is properly secured to prevent it falling down on the flexitank and potentially damaging the flexitank.

    NOTE: When filling the flexitank, DO NOT fill beyond capacity guidelines +/- 2%. Check and complete “Installation and Load Report” in the document pouch on the bulkhead.

  4. As the flexitank fills move the load hose higher to prevent it from being trapped between the side wall of the container and the flexitank.
  5. When the required amount of product has been loaded into the flexitank, close the flexitank valve by moving the handle to the closed position and turn off the pump simultaneously. Insert locking pin into handle to secure its position and seal as necessary.Ball Valve
  6. Prior to removing the loading hose from the flexitank valve, drain residual product from hose to a collection point.
  7. Clean the valve by removing any excess product and re-secure the bung cap.
  8. Ensure that the Warning Label has been affixed to the left hand door of the container. Close the right hand door of the container.

The loading process is complete.

For a pdf copy of this post, click the following link which will take you to the LinkedIn Profile of EPT Flexitank Sales Manager, Jennifer Phillips. Scroll down to the bottom and click How To Load a Top Discharge Flexitank. You may need to log into your existing LinkedIn account.

This is the fourth in a series of Flexitank Training Posts.

Click one of the following links to go to an earlier post:

How To Select A Flexitank Container

How To Prepare A Flexitank Container

How To Load A Bottom Discharge Flexitank


How to Load a Bottom Discharge BIG Red™ Flexitank

February 1, 2012
  1. Inspect the flexitank for proper installation.  Be sure to check the following items:

    a. Make sure that the flexitank has been properly unrolled completely against the walls of the container and into the corners. The flexitank should be secured to the container in all corners.

    b. Check the flexitank valve is secured against the bulkhead and is positioned correctly.

    c. Verify the capacity of the flexitank to avoid under or over-filling.  Flexitanks can be under or over loaded by up to 2% of the total capacity of the flexitank.NOTE:  Under or over filling beyond above recommendations may void  manufacturer’s warranty.

    d. Effective temperature range is 167°F to -23°F or 75°C to -5°C.

  2. Open the wear sleeve snout and roll back to expose the valve.
  3. Remove the safety cap and locking pin.  Pull the lever of the flexitank valve outward to ensure that the ball valve is fully opened.
  4. Fit the cam-lock coupling of the loading hose properly to the valve and lock into place. Make sure that the loading hose is properly supported to prevent pulling downward on the flexitank valve and potentially damaging the flexitank.
    NOTE:  When filling the flexitank, DO NOT fill beyond capacity guidelines +/- 2%.  Check and complete “Installation and Load Report” in the document pouch on the bulkhead.

  5. When the required amount of product has been loaded into the flexitank, close the flexitank valve by moving the handle to the closed position and turn off the pump simultaneously.  Insert locking pin into handle to secure its position and seal as necessary.
  6. Prior to removing the loading hose from the flexitank valve, drain residual product from hose to a collection point.
  7. Clean the valve by removing any excess product and re-secure the bung cap.
  8. Twist the snout of the wear sleeve closed and tighten with the attached zip-tie.  Fold out of the way of the door.
  9. Ensure that the Warning Label has been affixed to the left hand door of the container.  Close the right hand door of the container.
  10. The loading process is now complete.

    For a pdf copy of this post, click the following link which will take you to the LinkedIn Profile of EPT Flexitank Sales Manager, Jennifer Phillips.  Scroll down to the bottom and click How To Load a Bottom Discharge BIG Red Flexitank.  You may need to log into your existing LinkedIn account.

    This is the third in a series of Flexitank Training Posts.

    Click one of the following links to go to an earlier post:

    How To Select A Flexitank Container

    How To Prepare A Flexitank Container

     


Follow

Get every new post delivered to your Inbox.

Join 47 other followers